In Brighton and Hove, a 30m² rear dormer loft conversion costs around £53,000–£80,000 at a standard finish in 2026, a 15m² side return extension around £54,000–£71,500 and a 20m² single-storey rear extension around £63,000–£82,500, all including design, building control and VAT. With the average home in the city selling for £408,000 (ONS, August 2026), adding a bedroom or a kitchen-diner is often a cheaper route to more space than moving.

Last updated: October 2026 · Figures compiled from published UK cost data (sources listed at the end) · How we calculate costs

How much does an extension or loft conversion cost in Brighton?

Brighton and Hove packs a lot of very different housing into a narrow strip between the Downs and the sea: Regency squares and crescents on the seafront, steep Victorian terraces in Hanover and Round Hill, red-brick villas in Preston Park and Hove, and interwar semis and bungalows in Patcham, Hangleton, Woodingdean and Saltdean. Building costs follow South East labour and materials prices, and the city’s tight streets and hills add to them. The table below shows our modelled 2026 totals for the projects we see most often, at three finish levels.

ProjectSizeBasicStandardHigh-end
Side return extension15m²£43,500 – £58,500£54,000 – £71,500£66,500 – £91,000
Single-storey rear extension20m²£52,000 – £68,000£63,000 – £82,500£77,000 – £105,500
Kitchen extension with mid-range kitchen25m²£82,500 – £120,000£96,500 – £138,000£114,000 – £166,500
Two-storey extension (planning)40m²£91,500 – £117,000£111,000 – £143,000£136,000 – £183,500
Rear dormer loft conversion30m²£47,500 – £70,500£53,000 – £80,000£65,500 – £95,000
Hip to gable loft conversion30m²£58,000 – £81,500£63,500 – £91,000£78,500 – £109,500
Mansard loft conversion (planning)35m²£74,500 – £110,000£82,500 – £123,500£104,000 – £149,500
Garage conversion15m²£11,000 – £16,500£15,000 – £22,000£20,000 – £29,000

Totals use our calculator method with the South East regional multiplier of 1.12 (October 2026), about 12% above our national base. They include design, a structural engineer, building control, a lawful development certificate (£274) or householder planning fee (£548 for the “planning” rows) and VAT at 20%. The kitchen row includes a £15,000–£30,000 kitchen. Party wall fees, highway licences and contingency are not included. These are modelled figures, not quotes.

Our South East figures sit about 10% below our London figures and about 8% above the South West. In practice, Brighton quotes often land in the upper half of each range because so many jobs involve restricted access, steep sites, conservation area materials or scaffolding over a pavement. A plain rear dormer on a 1930s semi in Patcham or Hangleton is more likely to sit near the lower end. For a fuller breakdown of each project, see our house extension cost guide and loft conversion cost guide.

Brighton build cost per m² (standard finish, before VAT)

  • Side return extension: £2,800–£3,472 per m²
  • Single-storey rear or kitchen extension: £2,464–£3,024 per m²
  • Two-storey extension: £2,184–£2,688 per m²

These are modelled South East rates, not quotes. Side returns cost more per square metre because they are small, need steelwork bearing on or near the party wall and usually carry a glazed roof. Two-storey extensions cost less per m² because the foundations and roof serve two floors.

Pick “South East” as your region in our calculator and enter your own floor area for a Brighton estimate in seconds.

Calculate my Brighton extension cost

Brighton and Hove homes: what you are likely to be extending

The city grew outward from the old town and seafront in waves. Regency and early Victorian building fills the centre and Kemp Town, later Victorian terraces climb the valleys to the north and east, Hove grew as a planned suburb of villas and terraces, and the interwar years added semis and bungalows around the edges. Each type points to a different first project, and the planning picture changes sharply from one street to the next.

Victorian terraces in Hanover, Round Hill, Fiveways and Preston Park

These two-storey terraces, often with a narrow rear outrigger and a small yard or garden, are the backbone of the city’s family housing. They suit the same pairing seen across the South East:

Two things push costs up here. First, many streets are steep, so scaffolding needs more levelling and materials often have to be carried by hand from the road. Second, Round Hill and Preston Park are conservation areas, and Round Hill also has an Article 4 direction, so roof and frontage work that would be permitted development elsewhere may need planning permission. Check your address before paying for drawings.

Hove villas and Edwardian streets

Central Hove, including The Avenues, The Drive, Cliftonville and the streets around Hove station, has larger late-Victorian and Edwardian houses, many now split into flats. Conservation area and Article 4 controls are extensive here (see below). Where a house is still a single home, a rear kitchen extension or a modest rear dormer is the usual project. If the building is in flats, permitted development rights for houses do not apply at all, so even a small rear extension needs a planning application.

Regency squares and seafront terraces

Brunswick, Adelaide Crescent, Palmeira Square, Kemp Town and the seafront terraces are mostly listed buildings and largely converted to flats. Extensions here are specialist heritage projects needing listed building consent as well as planning, and our standard cost table is only a loose guide. Budget in the high-end column at least, and expect a longer design and consent stage.

Interwar semis and bungalows on the edges

Patcham, Withdean, Westdene, Hangleton, Woodingdean, Saltdean and Rottingdean have plenty of 1930s semis and bungalows with hipped roofs and side drives. These suit a hip-to-gable loft conversion with a rear dormer, a full-width single-storey kitchen extension or a garage conversion. Bungalows offer the biggest loft gains, though many sit on sloping sites cut into the chalk, which can add to foundation and drainage costs. Patcham and Rottingdean village cores are conservation areas with their own Article 4 directions.

Planning permission in Brighton and Hove

The planning authority is Brighton & Hove City Council. Many single-storey rear extensions and rear dormers on houses (not flats) can go ahead under permitted development, as long as you stay within the national limits: 3m deep for terraced and semi-detached houses and 4m for detached houses on a single-storey rear extension, and 40m³ (terraces) or 50m³ (semis and detached) of extra roof volume for a loft. If you rely on permitted development, we recommend a lawful development certificate (£274). Anything bigger, or anything in a conservation area or Article 4 area that the direction covers, needs a householder application (£548 in England from 1 April 2026). Our extension planning guide and loft planning guide explain the national rules in detail.

Design guidance: SPD12

The council’s main householder guidance is SPD12: Design Guide for Extensions and Alterations. An updated version was agreed for adoption by the council’s Tourism, Equalities, Communities and Culture Committee on 16 January 2020. It sets out what the council expects for rear and side extensions, dormers, rooflights and roof alterations, and it is the document planning officers will quote if they ask for changes. Read the dormer section before you brief a designer: a dormer that stays well below the ridge, is set in from the eaves and party walls and is clad to match the roof is much more likely to be approved where planning is needed.

Conservation areas

Brighton and Hove has 34 conservation areas, ranging from the Regency seafront to Victorian suburbs such as Round Hill, Preston Park, Hove Station and Old Hove, and village cores such as Patcham, Rottingdean and Ovingdean. Inside a conservation area, side extensions, two-storey rear extensions and any roof extension need planning permission, and cladding the outside of the house is restricted. Street-facing dormers are rarely approved.

Article 4 directions

The council has an unusually long list of heritage Article 4 directions, which typically mean planning permission is needed for minor work such as porches, replacement windows and doors, new roof coverings and painting the outside of a house. Most cover street-facing elevations, but some also cover rear extensions or back gardens. Directions listed by the council include:

  • Round Hill conservation area and West Hill conservation area
  • The Avenues (including the Cliftonville extension and The Drive), and Cliftonville, Denmark Villas and The Drive
  • Brunswick, Adelaide Crescent, Palmeira Square and Western Road, Lansdowne Square and Lansdowne Place, and Pembroke and Princes
  • Patcham and Rottingdean conservation areas

There is also an Article 4 direction removing the right to change a family house into a small house in multiple occupation (HMO) in the parts of the city it covers. If you are adding a loft room to a house you let to students in areas near the universities, check whether the change of use needs consent before you plan the layout.

Practical Brighton factors: access, licences and neighbours

  • Parking: large parts of central Brighton and Hove are in controlled parking zones. Budget for bay suspensions or trade permits for the skip, deliveries and the builder’s van, and ask your builder to include them in the quote.
  • Skips and scaffolding: a skip or scaffold on the pavement or road needs a licence from the council as highway authority. Your skip firm or scaffolder usually applies, but the cost is passed on to you. A rear dormer on a terrace with no rear access often needs scaffolding at the front as well as the back.
  • Access: few Victorian terraces have rear lanes, so steels, blocks and waste go through the house. On the steepest streets in Hanover, Elm Grove and Round Hill, allow for extra labour time and protection of hallways.
  • Party walls: side returns and lofts on terraces and semis almost always involve the Party Wall Act. Budget £1,000–£3,000 per neighbour if they appoint their own surveyor. See our party wall surveyor cost guide.

Real example: rear dormer on a mid-terrace near Preston Park

This is a modelled scenario, not a quote. A two-bedroom Victorian mid-terrace outside any conservation area adds a full-width rear dormer, creating a 30m² loft with a double bedroom and shower room. The work stays within permitted development volume limits, so a lawful development certificate is used rather than a planning application. Standard finish.

  • Dormer conversion including design, structural engineer, building control, certificate and VAT: £53,000 – £80,000
  • Party wall surveyors for two neighbours: £2,000 – £6,000
  • Estimated total: £55,000 – £86,000 (about £60,500 – £94,500 with a 10% contingency)

If the same house were in Round Hill, the dormer would need planning permission, adding the £548 fee, more design time and an eight-week wait, and the council may ask for a smaller, set-back dormer. Parking bay suspensions and scaffold licences are extra.

Loft conversion Brighton: which type suits your house?

  • Victorian terrace outside a conservation area: a rear dormer, often L-shaped over the outrigger. Usually permitted development.
  • Terrace in Round Hill, Preston Park or another conservation area: a modest, set-back rear dormer or rooflights only, with a planning application. Follow SPD12 closely.
  • 1930s hipped-roof semi in Patcham or Hangleton: a hip-to-gable conversion with a rear dormer gives the most headroom.
  • Bungalow in Woodingdean or Saltdean: dormers to one or both sides, or a new roof, depending on the existing pitch. A mansard is uncommon outside the Regency centre.

Our loft conversion cost calculator works out a figure for your own floor area.

House extension Brighton: common choices

On terraces, a side return or a wrap-around (side return plus a short rear extension) is the usual route to an open-plan kitchen-diner, though small yards limit how far you can go before you lose the garden altogether. On interwar semis, a full-width kitchen extension of 3m to 4m is the most common choice, sometimes paired with a garage conversion. Two-storey rear extensions need planning permission and the council will check the effect on neighbours’ light and outlook, which on closely packed streets can be decisive. See our two-storey extension cost guide for detail.

Timeline for a Brighton project

  1. Measured survey and drawings: 3–6 weeks.
  2. Lawful development certificate or planning decision: the statutory target is 8 weeks. Party wall notices can run alongside.
  3. Build: roughly 6–10 weeks for a rear dormer, 10–14 weeks for a side return and 16–24 weeks for a two-storey extension.
  4. Completion certificate: issued by building control after the final inspection.

Does extending add value in Brighton?

ONS and HM Land Registry data put the average Brighton and Hove price at £408,000 in August 2026 (provisional), down 2.1% on a year earlier. By type, detached homes averaged £855,000, semi-detached £548,000, terraced £476,000 and flats £295,000. The gap between the average terrace and the average semi is about £72,000, which is roughly the cost of a standard rear dormer plus contingency. That is why a third bedroom in the loft is such a common Brighton project: it moves a two-bed terrace into a more competitive bracket without the stamp duty and fees that come with moving.

That does not mean every pound comes back. The ceiling for a street is set by what the best houses on it have sold for, so compare sold prices for extended and unextended homes nearby before choosing a high-end finish. For funding options, see how to finance an extension.

Ways to keep a Brighton project on budget

  • Check designations first: confirm whether you are in one of the 34 conservation areas or an Article 4 area before paying for drawings.
  • Design to SPD12 from the start: a dormer drawn to the council’s guidance avoids a costly redesign after a refusal.
  • Get access costs itemised: parking suspensions, scaffold licences and hand-carrying on steep streets are easy to leave out of a quote.

Other towns and cities nearby

Compare extension and loft conversion costs in other areas we cover:

See every town on our extension costs by city page.

Brighton extension and loft conversion FAQs

How much is a loft conversion in Brighton?

A 30m² rear dormer costs around £53,000–£80,000 at a standard finish in 2026, and a hip-to-gable conversion on a 1930s semi around £63,500–£91,000, including design, building control and VAT.

How much does a side return extension cost in Brighton?

A 15m² side return costs around £54,000–£71,500 at a standard finish, before party wall fees. Steep streets and no rear access can push quotes towards the top of that range.

How many conservation areas does Brighton and Hove have?

There are 34 conservation areas, including Round Hill, Preston Park, Brunswick Town, Kemp Town, Patcham and Rottingdean. Roof extensions and side extensions in them need planning permission.

Do I need planning permission for a dormer in Brighton?

Not usually for a rear dormer on a house within the permitted development volume limits, unless the house is in a conservation area, is listed, or is a flat. In those cases you need a planning application and the council will judge it against SPD12.

What does an Article 4 direction mean for my Brighton house?

It removes some permitted development rights, so work such as new windows, porches, roof coverings or painting the front can need planning permission. The council lists directions for areas including Round Hill, West Hill, The Avenues, Brunswick, Patcham and Rottingdean.

Can I extend a flat in Brighton or Hove?

Flats have no householder permitted development rights, so any extension or loft conversion needs planning permission and, usually, the freeholder’s consent. Many seafront and Hove villa buildings are also listed.

Is it cheaper to extend than move in Brighton?

Often, yes. The average Brighton and Hove semi sold for about £72,000 more than the average terrace in August 2026. A standard rear dormer costs a similar amount, and you avoid stamp duty, agents’ fees and removal costs.

Get free quotes from builders in Brighton

Tell us about your Brighton home and what you want to build, and we’ll pass your details to local extension and loft conversion builders. Free and with no obligation.

Before you choose a builder, use our guide to comparing extension quotes to check each price like for like.

Get my free quotes


Sources and methodology

  • ONS, Housing prices in Brighton and Hove, August 2026 data (provisional), accessed October 2026.
  • Brighton & Hove City Council, Article 4 directions (heritage and change of use directions), accessed October 2026.
  • Brighton & Hove City Council, SPD12: Design Guide for Extensions and Alterations; updated SPD agreed for adoption 16 January 2020.
  • Brighton & Hove City Council, Conservation areas (34 areas), accessed October 2026.
  • England planning application fees from 1 April 2026 (householder £548; lawful development certificate for proposed use £274).
  • Extension Costs, How we calculate costs, South East multiplier 1.12, October 2026.